Policy
Updating task status updates resource status
Microsoft Office 5532.1000
Policy overview
Key metadata and intent for this policy.
Automatically updates resource status, such as actual and remaining work and cost, whenever you update task status, such as percent complete, actual duration, or remaining duration. If you enable this setting, task status updates are automatically applied to resources. If you disable or do not configure this setting, the user's default setting is used.
Internal name
L_PjUpdatingTask
Policy ID
924bc849ccfc
Elements
0
Registry values
How enabled and disabled states update the registry.
| Registry location | Type | Enabled value | Disabled value |
|---|---|---|---|
| HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\auto track resources | REG_DWORD | 1 | 0 |
Policy elements
Inputs and configuration options exposed by this policy.
This policy has no additional user input fields.
Other policies in this category
Explore related policies at the same level.
- UserActual costs are always calculated by Microsoft ProjectWindows7
- UserAnd move end of completed parts forward to status dateWindows7
- UserAnd move start of remaining parts back to status dateWindows7
- UserCalculate multiple critical pathsWindows7
- UserDefault fixed costs accrualWindows7
- UserEdits to total actual cost will be spread to the status dateWindows7
- UserEdits to total task % complete will be spread to the status dateWindows7
- UserInserted projects are calculated like summary tasksWindows7
- UserMove end of completed parts after status date back to status dateWindows7
- UserMove start of remaining parts before status date forward to status dateWindows7
- UserTasks are critical if slack is less than or equal toWindows7