Calculate multiple critical paths
Microsoft Office 5532.1000
Policy overview
Key metadata and intent for this policy.
Specifies that Project should calculate and display a critical path for each independent network of tasks within the project. If you enable this setting, Project will calculate multiple critical paths. If you disable or do not configure this setting, the user's default setting is used.
Internal name
L_PjCalcMultipleCriticalPaths
Policy ID
d6ed855e6801
Elements
0
Registry values
How enabled and disabled states update the registry.
| Registry location | Type | Enabled value | Disabled value |
|---|---|---|---|
| HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\calculate multiple critical paths | REG_DWORD | 1 | 0 |
Policy elements
Inputs and configuration options exposed by this policy.
This policy has no additional user input fields.
Other policies in this category
Explore related policies at the same level.
- UserActual costs are always calculated by Microsoft ProjectWindows7
- UserAnd move end of completed parts forward to status dateWindows7
- UserAnd move start of remaining parts back to status dateWindows7
- UserDefault fixed costs accrualWindows7
- UserEdits to total actual cost will be spread to the status dateWindows7
- UserEdits to total task % complete will be spread to the status dateWindows7
- UserInserted projects are calculated like summary tasksWindows7
- UserMove end of completed parts after status date back to status dateWindows7
- UserMove start of remaining parts before status date forward to status dateWindows7
- UserTasks are critical if slack is less than or equal toWindows7
- UserUpdating task status updates resource statusWindows7