Edits to total actual cost will be spread to the status date
Jump to overview

Policy overview

Key metadata and intent for this policy.

User
Category
Microsoft Project 2016 > Project Options > Calculation > Calculation options for 'Project1'
Supported on
Windows7

Distributes the changes to total actual cost evenly across the schedule to the status date (or to the current date if you have not specified a project status date). If you enable this setting, Project will distribute edits to actual cost evenly across a task up to the status date. If you disable or do not configure this setting, the user's default setting is used.

Internal name
L_PjEditToTotalSpread
Policy ID
32852bc9f2f5
Elements
0

Registry values

How enabled and disabled states update the registry.

ScopeRegistry locationTypeEnabled valueDisabled valueCopy
User
Path
software\policies\microsoft\office\16.0\ms project\options\calculation
Value name
edits to total actual cost will be spread to the status date
REG_DWORD
HKCU
1
HKCU
0
Registry location
Type REG_DWORD · User
Path
software\policies\microsoft\office\16.0\ms project\options\calculation
Value name
edits to total actual cost will be spread to the status date
Hive
HKCU
Enabled value
1
Disabled value
0

Policy elements

Inputs and configuration options exposed by this policy.

This policy has no additional user input fields.