Microsoft Office 5532.1000
Policy overview
Key metadata and intent for this policy.
Moves the completed portion of a task back to finish at the status date. If you enable this setting, the completed portion of the task moves back to finish at the status date. If you disable or do not configure this setting, the user's default setting is used.
Internal name
L_PjMoveCompleted
Policy ID
6aab06bfde04
Elements
0
Registry values
How enabled and disabled states update the registry.
| Registry location | Type | Enabled value | Disabled value |
|---|---|---|---|
| HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\movecompleted | REG_DWORD | 1 | 0 |
Policy elements
Inputs and configuration options exposed by this policy.
This policy has no additional user input fields.
Other policies in this category
Explore related policies at the same level.
- UserActual costs are always calculated by Microsoft ProjectWindows7
- UserAnd move end of completed parts forward to status dateWindows7
- UserAnd move start of remaining parts back to status dateWindows7
- UserCalculate multiple critical pathsWindows7
- UserDefault fixed costs accrualWindows7
- UserEdits to total actual cost will be spread to the status dateWindows7
- UserEdits to total task % complete will be spread to the status dateWindows7
- UserInserted projects are calculated like summary tasksWindows7
- UserMove start of remaining parts before status date forward to status dateWindows7
- UserTasks are critical if slack is less than or equal toWindows7
- UserUpdating task status updates resource statusWindows7