Policy
Tasks will always honor their constraint dates
Microsoft Office
Policy overview
Key metadata and intent for this policy.
Specifies that Project schedules tasks according to their constraint dates. If you enable this setting, task constraints will always be honored when tasks are scheduled. If you disable or do not configure this setting, the user's default setting is used.
Internal name
L_PjTasksHonorConstraints
Policy ID
9e6444cc5b71
Elements
0
Registry values
How enabled and disabled states update the registry.
| Scope | Registry location | Type | Enabled value | Disabled value | Copy |
|---|---|---|---|---|---|
| User | Path software\policies\microsoft\office\16.0\ms project\options\scheduling Value name honorconstraints | REG_DWORD | HKCU 1 | HKCU 0 |
Registry location
Path
software\policies\microsoft\office\16.0\ms project\options\scheduling
Value name
honorconstraints
Hive
HKCU
Enabled value
1
Disabled value
0
Policy elements
Inputs and configuration options exposed by this policy.
This policy has no additional user input fields.