Specifies the unit of time (minutes, hours, days, weeks, or months) used by default in the Duration field. If you enable this setting, the unit you specify will be used if the user does not specify a unit of time when entering a duration. If you disable or do not configure this setting, the user's default setting is used.

Internal name
L_PjDurationUnits
Policy ID
77e0d5f5d37c
Elements
1

Registry values

How enabled and disabled states update the registry.

No explicit registry values are set for enabled or disabled states.

Policy elements

Inputs and configuration options exposed by this policy.

ScopeElementTypeRegistry mappingConstraints & behaviorCopy
User
Duration is entered in
ID L_pjdurationunits23
enum
Path
software\policies\microsoft\office\16.0\ms project\options\scheduling
Value name
default duration units
Type
REG_DWORD
Options: Minutes (3), Hours (5), Days (7), Weeks (9), Months (11)
Duration is entered in
User · Type enum
Registry mapping
Path
software\policies\microsoft\office\16.0\ms project\options\scheduling
Value name
default duration units
Type
REG_DWORD
Details