Edits to start and finish dates
Jump to overview

Policy overview

Key metadata and intent for this policy.

User
Category
Microsoft Project 2016 > Project Options > Interface > Show indicators and Option butons for
Supported on
Windows7

Specifies that the feedback triangle should appear in a corner of the Duration field or the Task Name field if you change a task's work, units, or duration. If you enable this setting, a feedback triangle is displayed in the corner of the Duration or Task Name field if the user changes the task's work, units, or duration. If you disable or do not configure this setting, the user's default setting is used.

Internal name
L_PjEnterDateOOUI
Policy ID
bf110aa5b52c
Elements
0

Registry values

How enabled and disabled states update the registry.

ScopeRegistry locationTypeEnabled valueDisabled valueCopy
User
Path
software\policies\microsoft\office\16.0\ms project\options\interface
Value name
enterdateooui
REG_DWORD
HKCU
1
HKCU
0
Registry location
Type REG_DWORD · User
Path
software\policies\microsoft\office\16.0\ms project\options\interface
Value name
enterdateooui
Hive
HKCU
Enabled value
1
Disabled value
0